Installation of a transformer with a capacity of 75/125 MVA at a voltage of 330/33kV on the “Prokat” substation

  Within the framework of the project, the following was carried out:

  • installation of a 75/125 MVA transformer with a voltage of 330/33 kV with an oil receiver device;
  • installation of a high-voltage gas switch, disconnector and earthing device, OPN, TT and TN;
  • device of bus supports with a clamp for 330 kV wires;
  • device of bus supports with a clamp for 110 kV wire;
  • device of phase-shielded current line with cast insulation 33 kV;
  • connection of the transformer to GRU-33kV the second section of tires of PS “Prokat”;
  • in GRU-33kV PS “Prokat” an additional 33kV section was performed;
  • FKU 33kV device;
  • RZiA devices;
  • the device of the fire extinguishing and oil disposal system;
  • laying of control and power cables.

“The generating facility “Gomel II”, the site “Elsk”

Within the framework of the project was carried out:

  • construction of a complete photovoltaic plant according to the initial data of the equipment supplier company with a total maximum installed electric capacity of up to 14.31 MW (14.256 MW);
  • construction of the 110 kV “Vishenka” substation for the output of the photovoltaic power plant (hereinafter referred to as the FES) to the power grid;
  • connection to the power grid networks by performing the entry-exit of the 110 kV “Elsk-Makhnovichi” overhead line to the 110 kV “Vishenki” substation;
  • installation of a factory modular auxiliary building on the territory of the FES;
  • replacement of 110 kV overhead line protections with PS-110 kV “Elsk”;
  • laying of the fiber-optic cable to the 110 kV “Elsk” substation.

“Construction of an overhead transmission line 110 kV on the territory of the FEZ” Vitebsk “Sector 1” / Design of 110kV overhead lines with OPGT and fiber optic cable laying

 Within the framework of the project, the following was carried out:

  • construction of a double-chain 110 kV overhead line with an OKGT for connecting a new 110 kV “Zhurzhevo” substation by soldering off the existing 110 kV overhead line “Vitebsk-330 – Vitebsk CHPP”;
  • laying of the fiber-optic cable from the support No. 3 of the projected 110 kV overhead line to the 110 kV “KSM” PS.