  • “The generating facility “Gomel II”, the site “Elsk”

“The generating facility “Gomel II”, the site “Elsk”

VIEW LIST

Within the framework of the project was carried out:

  • construction of a complete photovoltaic plant according to the initial data of the equipment supplier company with a total maximum installed electric capacity of up to 14.31 MW (14.256 MW);
  • construction of the 110 kV “Vishenka” substation for the output of the photovoltaic power plant (hereinafter referred to as the FES) to the power grid;
  • connection to the power grid networks by performing the entry-exit of the 110 kV “Elsk-Makhnovichi” overhead line to the 110 kV “Vishenki” substation;
  • installation of a factory modular auxiliary building on the territory of the FES;
  • replacement of 110 kV overhead line protections with PS-110 kV “Elsk”;
  • laying of the fiber-optic cable to the 110 kV “Elsk” substation.