  • Modernization of arc steelmaking furnaces DSP-6N2  Customer: JSC “BELAZ” – the management company of the holding “BELAZ-HOLDING”, Zhodino, Belarus.

Modernization of arc steelmaking furnaces DSP-6N2 Customer: JSC “BELAZ” – the management company of the holding “BELAZ-HOLDING”, Zhodino, Belarus.

VIEW LIST

As part of the modernization project, the development, manufacture, supply and commissioning of chipboard control systems was carried out, which includes the following main elements:

  • Automated furnace control system based on Simatic S7-300 PLC (Siemens).
  • Power control system for arc steelmaking furnaces Men Expert (Pure metals Technologies Austria GmbH).
  • Hydraulic control system for the movement of electrodes, furnace mechanisms.
  • Auxiliary equipment management subsystem.
  • A system for collecting and recording data on the operation of furnaces of the steel shop (upper-level system).